GAIL (India) Ltd., the state-owned gas utility, has announced a capital investment of ₹844 crore to expand the capacity of its Dahej-Uran-Dabhol-Panvel (DUPL-DPPL) natural gas pipeline system. Currently operating at 19.9 million standard cubic meters per day (mmscmd), the network’s capacity will be enhanced to 22.5 mmscmd over the next three years. The company’s Board of Directors approved the decision on June 23.
Mumbai-Nagpur-Jharsuguda Pipeline Delayed, Cost Revised
In a related development, GAIL has revised the completion timeline for its 1,702-km Mumbai-Nagpur-Jharsuguda Pipeline (MNJPL) project. Originally set for completion by June 30, 2025, the new target is now September 30, 2025. Project costs have escalated by ₹411.12 crore to a revised total of ₹8,255.37 crore, up from the initially approved ₹7,844.25 crore.
The delay is largely due to hurdles in securing forest, National Board for Wildlife (NBWL), and highway clearances. Despite these challenges, the company has achieved substantial progress: 98% of the Nagpur-Jharsuguda and 97% of the Nagpur-Jabalpur segments are already complete, with remaining work held up by land acquisition issues.
Srikakulam-Angul Pipeline Timeline Extended
GAIL has also extended the deadline for its 744-km Srikakulam-Angul pipeline project. GAIL initially targeted project completion for June 2025 but now expects to finish it by December 2025. Out of the planned 322 km of spur lines, the company has already laid 252 km.
GAIL Strengthens Gas Infrastructure Amid Rising Demand
These developments underscore GAIL’s continued efforts to strengthen India’s natural gas infrastructure in line with rising demand and the country’s broader energy transition goals. Despite delays, the company remains committed to completing key pipeline projects and improving supply reliability across regions.




























