KSB Limited bagged a significant order from Larsen & Toubro (L&T) to supply boiler feed pump packages for NTPC’s upcoming supercritical thermal power plants—Gadarwara STPP Stage-II (2×800 MW) and Nabinagar STPP Stage-II (3×800 MW).
Comprehensive Package of 15 Pump Sets
KSB will deliver 15 complete sets of equipment, including main boiler feed pumps, booster pumps, motors, and accessories. These systems will support high-efficiency, supercritical power generation at the two sites.
Delivery Timeline and Payment Structure
KSB will deliver the equipment over a period of 20 to 28 months from the date of contract signing. The contract outlines staggered payment terms, tied to the achievement of specific project milestones.
Strengthening Presence in Power Infrastructure
As reported by projectstoday.com, the order marks a key milestone for KSB in expanding its presence in India’s conventional energy sector. The deployment of KSB’s advanced pump systems underscores the company’s critical role in supporting the nation’s power infrastructure.